Requirements for Overhead Cost Claims and Construction Dispute Resolution Mechanisms in Indonesia: A Normative Study

  • Qadri Qadri Universitas Pekalongan, Indonesia
  • S. Sami’an Universitas Pekalongan, Indonesia
  • Adi Saputro Universitas Pekalongan, Indonesia

Abstract

Overhead cost claim disputes are a crucial issue in Indonesia’s construction industry. Therefore, this research aims to comprehensively analyze the legal aspects of overhead cost claims in construction contracts in Indonesia, encompassing the legal basis, types of claimable costs, legal conditions triggering claims, claim submission requirements, calculation methods, and dispute resolution mechanisms. A normative juridical method is employed to achieve this objective, using a statute, case, and conceptual approach. Data is sourced from statutory regulations, construction contract standards, jurisprudence, and legal literature and then analyzed qualitatively. Substantively, this research finds that the legal basis for overhead cost claims in Indonesia involves a complex interaction between Law Number 2 of 2017, Government Regulation Number 22 of 2020, the Civil Code, and contract standards such as FIDIC. Furthermore, overhead claims must be based on wanprestasi (breach of contract), force majeure, or variation orders and must meet the requirements of notification, documentation, accountable calculation, and causality. In terms of calculation, the accepted method must be by the principle of compensation. As for dispute resolution, it can be through mediation, conciliation, arbitration, or litigation, with the caveat that the selection of a mechanism depends on a case-by-case analysis. Overall, this research provides a comprehensive understanding of the legal aspects of overhead cost claims in construction contracts in Indonesia.

Keywords: Claim Requirements, Construction Contract, Dispute Resolution, Overhead Costs

Article Metrics

Downloads

Download data is not yet available.

References

Abdelalim, A. M., Al-Sabah, R., Salem, M., Said, S. O., Tantawy, M., & Al-Regal, M. R. E. (2024). Variations and Claims in International Construction Projects in the MENA Region from the Last Decade. Buildings, 14(8), 1-35. https://doi.org/10.3390/buildings14082496

Ali, B., Aibinu, A. A., & Paton-Cole, V. (2022). An Investigation of Difficulties in Information Management for Delay and Disruption Claims. In Proceedings of the World Building Congress 2022 (Vol. 1101, pp. 1-9). IOP Conference Series: Earth and Environmental Science. https://doi.org/10.1088/1755-1315/1101/5/052023

Antoniou, F., & Tsioulpa, A. V. (2024). Assessing the Delay, Cost, and Quality Risks of Claims on Construction Contract Performance. Buildings, 14(2), 1-18. https://doi.org/10.3390/buildings14020333

Awwad, R., & Thabet, Z. (2022). Effect of Implementing Sustainable Management Practices on Claims Mitigation in Construction Projects. Proceedings of International Structural Engineering and Construction, 9(1), 1-6. https://doi.org/10.14455/ISEC.2022.9(1).SUS-08

Colonial Regulations, Staatsblad Number 23 of 1847 on the Burgerlijk Wetboek voor Indonesie/the Civil Code. https://jdih.mahkamahagung.go.id/legal-product/kitab-undang-undang-hukum-perdata/detail

Dastyar, B., Esfahani, A. F., Askarifard, M., & Abbasi, A. M. (2018). Identification, Prioritization and Management of Construction Project Claims. Journal of Engineering, Project, and Production Management, 8(2), 90-96. https://doi.org/10.32738/JEPPM.201807.0004

Elbehairy, H. S., & Nagy, A. M. (2024). Identifying Causes of Claims in the Egyptian Construction Sector. Journal of Advanced Research in Applied Sciences and Engineering Technology, 35(2), 132-143. https://doi.org/10.37934/araset.35.2.132143

FIDIC. (2010). Conditions of Contract for Construction, MDB Harmonised Edition. International Federation of Consulting Engineers. https://fidic.org/books/construction-contract-mdb-harmonised-ed-version-3-june-2010-harmonised-red-book

FIDIC. (2017). Amendments to the FIDIC Conditions of Contract for Construction, Second Edition. International Federation of Consulting Engineers. https://fidic.org/books/construction-contract-2nd-ed-2017-red-book

Government Regulation in Lieu of Law of the Republic of Indonesia Number 2 of 2022 on Job Creation (State Gazette of the Republic of Indonesia of 2022 Number 238, Supplement to the State Gazette of the Republic of Indonesia Number 6841). https://peraturan.go.id/id/perppu-no-2-tahun-2022

Government Regulation of the Republic of Indonesia Number 22 of 2020 on the Implementing Regulation of Law Number 2 of 2017 on Construction Service (State Gazette of the Republic of Indonesia of 2020 Number 107, Supplement to the State Gazette of the Republic of Indonesia Number 6494). https://peraturan.go.id/id/pp-no-22-tahun-2020

Government Regulation of the Republic of Indonesia Number 14 of 2021 on Amendment to Government Regulation Number 22 of 2020 on the Implementing Regulation of Law Number 2 of 2017 on Construction Service (State Gazette of the Republic of Indonesia of 2021 Number 24, Supplement to the State Gazette of the Republic of Indonesia Number 6626). https://peraturan.go.id/id/pp-no-14-tahun-2021

Ilma, D. A. U., Ma’arif, F., Utoyo, B., Baldah, N., & Inayah, D. T. (2021). A Comparative Study of National and International Contracts Document Refers to the FIDIC Standard on Construction Projects in Indonesia. In P. A. Sari et al. (Eds.), Proceedings of the 1st International Conference on Economics Engineering and Social Science, InCEESS 2020 (pp. 1-7). European Alliance for Innovation. https://doi.org/10.4108/eai.17-7-2020.2303003

Indahwati, A. N., Sami’an, S., & Hardjomuljadi, S. (2025). Arbitration in Resolving Construction Cost Claim Disputes Due to Time Extensions: A Study of Contract Law in Indonesia. SIGn Jurnal Hukum, 6(2), 263-281. https://doi.org/10.37276/sjh.v6i2.388

Irwansyah. (2021). Penelitian Hukum: Pilihan Metode & Praktik Penulisan Artikel, Revision Edition. Mirra Buana Media.

Jayalath, C. (2023). Application of Technical Rationality and Reflective Practice in Managing Intricate Construction Claims: A Case Study in Qatar. Archives of Current Research International, 23(7), 173-193. https://doi.org/10.9734/acri/2023/v23i7603

Law of the Republic of Indonesia Number 30 of 1999 on Arbitration and Alternative Dispute Resolution (State Gazette of the Republic of Indonesia of 1999 Number 138, Supplement to the State Gazette of the Republic of Indonesia Number 3872). https://jdih.dpr.go.id/setjen/detail-dokumen/tipe/uu/id/431

Law of the Republic of Indonesia Number 2 of 2017 on Construction Service (State Gazette of the Republic of Indonesia of 2017 Number 11, Supplement to the State Gazette of the Republic of Indonesia Number 6018). https://jdih.dpr.go.id/setjen/detail-dokumen/tipe/uu/id/1687

Law of the Republic of Indonesia Number 6 of 2023 on Enactment of Government Regulation in Lieu of Law Number 2 of 2022 on Job Creation Into Law (State Gazette of the Republic of Indonesia of 2023 Number 41, Supplement to the State Gazette of the Republic of Indonesia Number 6856). https://jdih.dpr.go.id/setjen/detail-dokumen/tipe/uu/id/1825

Likhitruangsilp, V., Ioannou, P. G., & Van, S. Q. (2021). Analyzing the Interdependences of Claim Causes in Construction Projects. Proceedings of International Structural Engineering and Construction, 9(1), 1-7. https://doi.org/10.14455/ISEC.2022.9(1).LDR-01

Matseke, D. A., & Khatleli, N. (2021). Claims Management: Underlying Causes in Mega-Construction Projects. Proceedings of International Structural Engineering and Construction, 8(1), 1-6. https://doi.org/10.14455/ISEC.2021.8(1).CON-27

Matseke, D. A., Khatleli, N., & Root, D. (2022). An Overview of Multi-Criteria Decision Making Techniques in Construction Projects Claims Management. Proceedings of International Structural Engineering and Construction, 9(1), 1-6. https://doi.org/10.14455/ISEC.2022.9(1).LDR-03

Mirzaee, A. M., Edwards, D., & Thwala, W. D. (2023). Developing a Reference Framework for Claim Management Office: A Multi-Method Approach of an International Construction Firm. Buildings, 13(7), 1-18. https://doi.org/10.3390/buildings13071692

Muhlis, M., & Valdiansyah, M. (2023). Analisis Faktor-Faktor yang Mempengaruhi Klaim dan Strategi Penyelesaiannya dalam Industri Konstruksi. Jurnal Daktilitas, 3(1), 10-16. https://doi.org/10.36563/daktilitas.v3i1.816

Nugroho, R., & Hardjomuljadi, S. (2022). Pengaruh Kinerja Waktu dan Biaya Terhadap Munculnya Potensi Klaim di Proyek-Proyek Pembangkit Listrik Nasional pada Masa Pendemi COVID-19. Rekayasa: Jurnal Ilmiah Fakultas Teknik Universitas Lampung, 26(2), 49-52. https://doi.org/10.23960/rekrjits.v26i2.97

Okereke, R. A., Zakariyau, M., & Afonne, U. (2023). Assessment of Critical Claims and Their Impacts on the Construction Industry of Nigeria. Journal of Engineering and Technology for Industrial Applications, 9(41), 4-14. https://doi.org/10.5935/jetia.v9i41.858

Pasinggi, A., & Simanjuntak, M. R. A. (2024). Identify the Cause of Claims on Construction Contracts in the West Papua Provincial Government Area. Jurnal Indonesia Sosial Teknologi, 5(4), 1856-1865. https://doi.org/10.59141/jist.v5i4.1000

Piyumra, R. A. D., & Disaratna, P. A. P. V. D. S. (2023). Application of Experiential Knowledge and Personal Constructs Into Construction Claims Management. In Y. G. Sandanayake et al. (Eds.), Proceedings of the 11th World Construction Symposium (pp. 224-236). Ceylon Institute of Builders. https://doi.org/10.31705/WCS.2023.19

Praja, W. K. (2023). Factors Affecting the Effectiveness of Contractors’ All Risk Insurance Claims: A Study of State-Owned Contractors in Indonesia. Eduvest: Journal of Universal Studies, 3(9), 1724-1741. https://doi.org/10.59188/eduvest.v3i9.907

Qamar, N., & Rezah, F. S. (2020). Metode Penelitian Hukum: Doktrinal dan Non-Doktrinal. CV. Social Politic Genius (SIGn).

Sahu, P., Bera, D. K., & Parhi, P. K. (2024). Analyzing the Impact of Construction Delays on Disputes in India: A Statistical and Machine Learning Approach. Journal of Mechanics of Continua and Mathematical Sciences, 19(9), 24-34. https://doi.org/10.26782/jmcms.2024.09.00004

Sampara, S., & Husen, L. O. (2016). Metode Penelitian Hukum. Kretakupa Print.

Sebastian, R. R., Wisatrioda, B., Sami’an, S., & Hardjomuljadi, S. (2025). Resolving Construction Disputes through Negotiation: A Case Study of Amendments to the Environmental Impact Assessment for an Electricity Infrastructure Project. SIGn Jurnal Hukum, 6(2), 282-295. https://doi.org/10.37276/sjh.v6i2.389

Sumantri, M. F. A., Sami’an, S., & Hardjomuljadi, S. (2025). Concurrent Delay and Price Adjustment in Multi-Year Contracts: An Indonesian Construction Law Perspective. SIGn Jurnal Hukum, 6(2), 343-367. https://doi.org/10.37276/sjh.v6i2.399

Tamang, S., Kayastha, G. P., & Adhikari, P. (2024). Effects and Remedies of Construction Claims in Hydropower Projects: Case Studies of Selected Medium-Scale Hydropower Projects in Nepal. New Perspective: Journal of Business and Economics, 7(1), 109-118. https://doi.org/10.3126/npjbe.v7i1.70064

Thalib, P., Kholiq, M. N., & Wijaya, O. Y. A. (2023). Bank Guarantee Claims as Collateral for Beneficiary in Construction Projects. Russian Law Journal, 11(2), 250-259. https://doi.org/10.52783/rlj.v11i2.662

Triwijaya, H. Y., Sami’an, S., & Hardjomuljadi, S. (2025). Dispute Resolution Mechanism Related to Force Majeure Clauses in Construction Contracts: A Case Study of Procurement Process at the State-Owned Enterprises. SIGn Jurnal Hukum, 6(2), 401-417. https://doi.org/10.37276/sjh.v6i2.402

Wiraantaka, J. A., Sami’an, S., & Hardjomuljadi, S. (2025). Implementation of Legal Principles in Construction Service Agreements: A Normative Study. SIGn Jurnal Hukum, 6(2), 386-400. https://doi.org/10.37276/sjh.v6i2.401

Wisatrioda, B., Sebastian, R. R., Sami’an, S., & Hardjomuljadi, S. (2025). Resolving Hydropower Plant Construction Disputes through a Standing Dispute Board: A Case Study of Asahan 3 HEPP. SIGn Jurnal Hukum, 6(2), 296-312. https://doi.org/10.37276/sjh.v6i2.392

Wisnuaji, H., Sami’an, S., & Hardjomuljadi, S. (2025). Interpretation of Schedule When Changes in Conditions: A Case Study of Price Adjustment in the Lampung Extra High Voltage Overhead Line Construction Contract. SIGn Jurnal Hukum, 6(2), 368-385. https://doi.org/10.37276/sjh.v6i2.400

Yanuar, R., Saputro, A., & Sami’an, S. (2025). Sustainability of Infrastructure Development in Indonesia: A Legal Analysis of Price Adjustments in Construction Contracts. SIGn Jurnal Hukum, 6(2), 247-262. https://doi.org/10.37276/sjh.v6i2.385

Published
2025-02-17
How to Cite
Qadri, Q., Sami’an, S., & Saputro, A. (2025). Requirements for Overhead Cost Claims and Construction Dispute Resolution Mechanisms in Indonesia: A Normative Study. SIGn Jurnal Hukum, 6(2), 433-451. https://doi.org/10.37276/sjh.v6i2.404

Most read articles by the same author(s)

1 2 > >>