Effectiveness of the BANI Binding Opinion in the Resolution of Construction Contract Interpretation Disputes: A Case Study of the Kalimantan Steam Power Plant (2x5 MW) Project
Abstract
Construction disputes in Indonesia are often rooted in differences in the interpretation of contract clauses. This is reflected in the dispute between PT PLN (Persero) and PT XXX over the Kalimantan Steam Power Plant (2x5 MW) development project, regarding claims for an extension of time and additional cost compensation due to social access obstacles. This research aims to conduct a juridical analysis of problems in the interpretation of contract clauses. Additionally, this research constructs the legal basis for granting EoT and real cost compensation, and evaluates the effectiveness and executive power of the BANI Binding Opinion as an instrument of legal certainty. The research method used is normative juridical, through the statute and case approaches to the BANI Binding Opinion Number: XX/BO-BANI/2017 document, and the conceptual approach. The research results reveal that the interpretational deadlock was triggered by the parties’ failure to reach an agreement regarding the allocation of external obstacle risks beyond the contractor’s control. Therefore, BANI determined that a time extension and cost compensation should be granted using the actual implementation cost difference method, based on the principles of propriety and contractual justice, to restore the service provider’s economic position. It is concluded that the BANI Binding Opinion is a highly effective, efficient dispute resolution solution, and possesses stable executive power as regulated in Article 52 and Article 53 of Law Number 30 of 1999. This instrument provides the parties with final and binding legal certainty. This mechanism also mitigates the risk of project termination by registering the decision at the district court without going through an adversarial adjudication process.
Downloads
References
Barnado, G., & Karim, R. A. (2024). Dispute Resolution Strategies in Construction Projects to Mitigate Impacts on Time Performance – Project Owner’s Perspective. International Journal of Science, Technology & Management, 5(6), 1386-1397. https://doi.org/10.46729/ijstm.v5i6.1201
Colonial Regulations, Staatsblad Number 23 of 1847 on the Burgerlijk Wetboek voor Indonesie/the Civil Code. https://jdih.mahkamahagung.go.id/legal-product/kitab-undang-undang-hukum-perdata/detail
Ervianti, M. N., Setiadi, E., & Heniarti, D. D. (2025). Juridical Review of the Annulment of Arbitral Awards by the District Court: A Case Study of Decision No. 167/Pdt.P/2000/PN.Jkt.Pst. Pena Justisia: Media Komunikasi dan Kajian Hukum, 24(1), 8002-8009. https://doi.org/10.31941/pj.v24i1.6947
Government Regulation in Lieu of Law of the Republic of Indonesia Number 2 of 2022 on Job Creation (State Gazette of the Republic of Indonesia of 2022 Number 238, Supplement to the State Gazette of the Republic of Indonesia Number 6841). https://peraturan.go.id/id/perppu-no-2-tahun-2022
Indahwati, A. N., Sami’an, S., & Hardjomuljadi, S. (2025). Arbitration in Resolving Construction Cost Claim Disputes Due to Time Extensions: A Study of Contract Law in Indonesia. SIGn Jurnal Hukum, 6(2), 263-281. https://doi.org/10.37276/sjh.v6i2.388
Irwansyah. (2020). Penelitian Hukum: Pilihan Metode & Praktik Penulisan Artikel. Mirra Buana Media.
Junaedi, J., Saputro, A., & Sami’an, S. (2025). Challenges in Electrical Infrastructure Permitting: A Case Study of Substation Development in South Sumatra. SIGn Jurnal Hukum, 6(2), 313-327. https://doi.org/10.37276/sjh.v6i2.393
Lannyati, N., & Sami’an, S. (2025). Comprehending Non-Litigative Resolution of Construction Disputes Through Arbitration. Journal of Law, Politic and Humanities, 5(4), 2659-2669. https://doi.org/10.38035/jlph.v5i4.1599
Law of the Republic of Indonesia Number 18 of 1999 on Construction Service (State Gazette of the Republic of Indonesia of 1999 Number 54, Supplement to the State Gazette of the Republic of Indonesia Number 3833). https://www.dpr.go.id/dokumen/jdih/undang-undang/detail/419
Law of the Republic of Indonesia Number 30 of 1999 on Arbitration and Alternative Dispute Resolution (State Gazette of the Republic of Indonesia of 1999 Number 138, Supplement to the State Gazette of the Republic of Indonesia Number 3872). https://www.dpr.go.id/dokumen/jdih/undang-undang/detail/431
Law of the Republic of Indonesia Number 2 of 2017 on Construction Service (State Gazette of the Republic of Indonesia of 2017 Number 11, Supplement to the State Gazette of the Republic of Indonesia Number 6018). https://www.dpr.go.id/dokumen/jdih/undang-undang/detail/1687
Law of the Republic of Indonesia Number 6 of 2023 on Enactment of Government Regulation in Lieu of Law Number 2 of 2022 on Job Creation Into Law (State Gazette of the Republic of Indonesia of 2023 Number 41, Supplement to the State Gazette of the Republic of Indonesia Number 6856). https://www.dpr.go.id/dokumen/jdih/undang-undang/detail/1825
Lo, A., Lee, E. P., Chen, N. E., Baretta, N., Nugraha, D. P., & Tanaya, V. (2025). Legal Implications of Government Default in the Ranggulalo Market Construction Contract: An Analysis of Decision Number 28/Pdt.G/2021/PN Dgl. SIGn Jurnal Hukum, 7(1), 70-91. https://doi.org/10.37276/sjh.v7i1.416
Pertiwi, P. C., Nugroho, A. S. B., & Wibowo, R. A. (2024). Kajian Putusan Pengadilan yang Membatalkan Putusan Arbitrase BANI pada Sengketa Kontrak Jasa Konstruksi. Teras Jurnal: Jurnal Teknik Sipil, 14(2), 468-484. https://doi.org/10.29103/tj.v14i2.1148
Qadri, Q., Sami’an, S., & Saputro, A. (2025). Requirements for Overhead Cost Claims and Construction Dispute Resolution Mechanisms in Indonesia: A Normative Study. SIGn Jurnal Hukum, 6(2), 433-451. https://doi.org/10.37276/sjh.v6i2.404
Qamar, N., & Rezah, F. S. (2020). Metode Penelitian Hukum: Doktrinal dan Non-Doktrinal. CV. Social Politic Genius (SIGn). https://books.google.co.id/books?id=TAQHEAAAQBAJ
Rahmiko, E., Saputro, A., & Sami’an, S. (2025). Legal Dynamics in the Permitting Process for Extra High Voltage Overhead Line Development in South Sumatra. SIGn Jurnal Hukum, 6(2), 328-342. https://doi.org/10.37276/sjh.v6i2.394
Safnul, D., Kamello, T., Purba, H., & Ikhsan, E. (2024). Settlement of Contract Business Activities Disputes through Arbitration: Evidence from Construction Service Company. Calitatea, 25(201), 286-291. https://doi.org/10.47750/qas/25.201.31
Sampara, S., & Husen, L. O. (2016). Metode Penelitian Hukum. Kretakupa Print.
Samsiati, S., Kurniawan, F., Nugraha, X., & Hartono, J. (2022). Dispute Board in Construction Services: A Manifestation of the Principles of Quick, Simple, and Affordable Dispute Resolution. Environment-Behaviour Proceedings Journal, 7(SI11), 9-13. https://doi.org/10.21834/ebpj.v7iSI11.4166
Sebastian, R. R., Wisatrioda, B., Sami’an, S., & Hardjomuljadi, S. (2025). Resolving Construction Disputes through Negotiation: A Case Study of Amendments to the Environmental Impact Assessment for an Electricity Infrastructure Project. SIGn Jurnal Hukum, 6(2), 282-295. https://doi.org/10.37276/sjh.v6i2.389
Setiyawan, I. A., Pasaribu, D. M., & Hikmahtiar, R. (2025). The Legal Force of Change Order Instruction for the Work in Construction Contracts: A Case Study of Substation Development in Central Sumatra. SIGn Jurnal Hukum, 6(2), 452-467. https://doi.org/10.37276/sjh.v6i2.409
Sumantri, M. F. A., Sami’an, S., & Hardjomuljadi, S. (2025). Concurrent Delay and Price Adjustment in Multi-Year Contracts: An Indonesian Construction Law Perspective. SIGn Jurnal Hukum, 6(2), 343-367. https://doi.org/10.37276/sjh.v6i2.399
Triwijaya, H. Y., Sami’an, S., & Hardjomuljadi, S. (2025). Dispute Resolution Mechanism Related to Force Majeure Clauses in Construction Contracts: A Case Study of Procurement Process at the State-Owned Enterprises. SIGn Jurnal Hukum, 6(2), 401-417. https://doi.org/10.37276/sjh.v6i2.402
Waisapi, J. Y. (2024). Analysis of Construction Dispute Resolution Reform Perspective of Law Number 2 of 2017. Journal of Law, Politic and Humanities, 4(6), 2524-2537. https://doi.org/10.38035/jlph.v4i6.780
Wiraantaka, J. A., Sami’an, S., & Hardjomuljadi, S. (2025). Implementation of Legal Principles in Construction Service Agreements: A Normative Study. SIGn Jurnal Hukum, 6(2), 386-400. https://doi.org/10.37276/sjh.v6i2.401
Wisatrioda, B., Sebastian, R. R., Sami’an, S., & Hardjomuljadi, S. (2025). Resolving Hydropower Plant Construction Disputes through a Standing Dispute Board: A Case Study of Asahan 3 HEPP. SIGn Jurnal Hukum, 6(2), 296-312. https://doi.org/10.37276/sjh.v6i2.392
Wisnuaji, H., Sami’an, S., & Hardjomuljadi, S. (2025). Interpretation of Schedule When Changes in Conditions: A Case Study of Price Adjustment in the Lampung Extra High Voltage Overhead Line Construction Contract. SIGn Jurnal Hukum, 6(2), 368-385. https://doi.org/10.37276/sjh.v6i2.400
Yanuar, R., Saputro, A., & Sami’an, S. (2025). Sustainability of Infrastructure Development in Indonesia: A Legal Analysis of Price Adjustments in Construction Contracts. SIGn Jurnal Hukum, 6(2), 247-262. https://doi.org/10.37276/sjh.v6i2.385
Copyright (c) 2026 Anrizal Anrizal, Agung Aprianto, Ifdal Baharuddin, Ronald Lapasau, Sarwono Hardjomuljadi, S. Sami’an

This work is licensed under a Creative Commons Attribution 4.0 International License.
.jpg)