Interpretation of Schedule When Changes in Conditions: A Case Study of Price Adjustment in the Lampung Extra High Voltage Overhead Line Construction Contract

  • Haryo Wisnuaji Universitas Pekalongan, Indonesia
  • S. Sami’an Universitas Pekalongan, Indonesia
  • Sarwono Hardjomuljadi Universitas Pekalongan, Indonesia

Abstract

This normative legal research analyzes disparities in interpreting work execution timelines in implementing the price adjustment clause in the Lampung EHV Overhead Line Construction Contract, which were complicated by significant changes in circumstances. The change in the transmission line route caused delays, triggering differences in viewpoints between PLN and the contractor regarding the cut-off for price adjustment calculations. The contractor argues for using factual indicators of work completion, referring to the doctrine of rebus sic stantibus. Meanwhile, PLN adheres to indicators related to the initial commitment based on the principles of pacta sunt servanda and nemo auditur. This research uses statute, conceptual, and case approaches to examine the Lampung EHV Overhead Line Construction Contract. The research findings show that neither approach, if applied rigidly, produces a fair cut-off. Therefore, this research formulates normative parameters that link the cut-off to the most relevant indicator, plus an adjusted duration that considers the impact of changes in circumstances and internal contractor factors. These parameters aim to achieve contractual justice, legal certainty, and objective, transparent, and accountable implementation of price adjustment based on the principle of good faith.

Keywords: Changed Circumstances, Contract Interpretation, Cut-off Date, Execution Timeline, Price Adjustment

Article Metrics

Downloads

Download data is not yet available.

References

Adi, D. P. (2015). Absorbsi Prinsip “Rebus Sic Stantibus” dalam Kerangka Pembaharuan Hukum Perjanjian Nasional. Jatiswara, 30(1), 71-91. https://doi.org/10.29303/jtsw.v30i1.91

Decision of Minister of Energy and Mineral Resources of the Republic of Indonesia Number 188.K/HK.02/MEM.L/2021 on the Ratification of the Electricity Supply Business Plan of the State Electricity Company (Persero) for 2021 to 2030. https://jdih.esdm.go.id/dokumen/view?id=2192

Fulli-Lemaire, S. (2019). Les Restitutions Consécutives à L’annulation du Contrat Illicite Brèves Réflexions Sur Le Droit Français Réformé Des Contrats À Partir De L’arrêt. European Review of Private Law, 26(2), 265-271. https://doi.org/10.54648/erpl2018018

Indahwati, A. N., Sami’an, S., & Hardjomuljadi, S. (2025). Arbitration in Resolving Construction Cost Claim Disputes Due to Time Extensions: A Study of Contract Law in Indonesia. SIGn Jurnal Hukum, 6(2), 263-281. https://doi.org/10.37276/sjh.v6i2.388

Irwansyah. (2021). Penelitian Hukum: Pilihan Metode & Praktik Penulisan Artikel, Revision Edition. Mirra Buana Media.

Junaedi, J., Saputro, A., & Sami’an, S. (2025). Challenges in Electrical Infrastructure Permitting: A Case Study of Substation Development in South Sumatra. SIGn Jurnal Hukum, 6(2), 313-327. https://doi.org/10.37276/sjh.v6i2.393

Mariyati, D. (2018). Prinsip Hukum dalam Penyusunan dan Pelaksanaan Kontrak Engineering Procurement Construction (Kontrak “EPC”). Yuridika, 33(2), 188-211. https://doi.org/10.20473/ydk.v33i2.7412

Nachrawi, G., & Heliany, I. (2023). Karakteristik dan Penerapan Change Order pada Kontrak Kerja Konstruksi yang Terjadi di Indonesia. Iblam Law Review, 3(2), 536-546. https://doi.org/10.52249/ilr.v3i2.444

Negara, A. S., Rifai, A., & Shebubakar, A. (2024). Resiko Kontraktual Pelaksanaan Kontrak Engineering Procurement Construction (EPC) dengan Pola Pembiayaan Proyek. Unes Journal of Swara Justisia, 8(1), 223-236. https://doi.org/10.31933/995mz446

Norms, Standards, Procedures, and Criteria of the Directorate General of Highways Number SOP/UPM/DJBM-116 Rev:01 on Standard Operating Procedures for Price Adjustment. https://binamarga.pu.go.id/index.php/nspk/detail/sopupmdjbm-116-rev01-standar-operasional-prosedur-penyesuaian-harga-price-adjustment

Presidential Regulation of the Republic of Indonesia Number 16 of 2018 on Public Procurement of Goods/Services (State Gazette of the Republic of Indonesia of 2018 Number 33). https://peraturan.go.id/id/perpres-no-16-tahun-2018

Presidential Regulation of the Republic of Indonesia Number 12 of 2021 on Amendment to Presidential Regulation Number 16 of 2018 on Public Procurement of Goods/Services (State Gazette of the Republic of Indonesia of 2021 Number 63). https://peraturan.go.id/id/perpres-no-12-tahun-2021

Putri, R. R., Chandrawulan, A. A., & Amalia, P. (2018). Peringkat Arus Investasi Indonesia dalam Kerangka Asean-China Free Trade Agreement (Perbandingan dengan Singapura, Malaysia, Thailand, dan Vietnam) Ditinjau dari Prinsip Fair and Equitable Treatment. Jurnal Hukum & Pembangunan, 48(2), 275-298. https://doi.org/10.21143/jhp.vol48.no2.1664

Qamar, N., & Rezah, F. S. (2020). Metode Penelitian Hukum: Doktrinal dan Non-Doktrinal. CV. Social Politic Genius (SIGn).

Rahmiko, E., Saputro, A., & Sami’an, S. (2025). Legal Dynamics in the Permitting Process for Extra High Voltage Overhead Line Development in South Sumatra. SIGn Jurnal Hukum, 6(2), 328-342. https://doi.org/10.37276/sjh.v6i2.394

Rakasatutya, F., Yuslim, Y., & Andora, H. (2023). Kedudukan Denda Keterlambatan Pelaksanaan Pekerjaan Konstruksi dalam Kepailitan. Unes Journal of Swara Justisia, 7(2), 497-513. https://doi.org/10.31933/ujsj.v7i2.361

Rawls, J. (2001). Justice as Fairness: A Restatement. Harvard University Press.

Renyaan, W., Ingratubun, J. A., & Kliwon, K. (2022). Analisis Penyelesaian Sengketa Kontrak Kerja Konstruksi Proyek Pemerintah Melalui Non Litigasi. Jurnal Hukum Ius Publicum, 3(1), 82-96. https://doi.org/10.55551/jip.v3i1.47

Sampara, S., & Husen, L. O. (2016). Metode Penelitian Hukum. Kretakupa Print.

Sebastian, R. R., Wisatrioda, B., Sami’an, S., & Hardjomuljadi, S. (2025). Resolving Construction Disputes through Negotiation: A Case Study of Amendments to the Environmental Impact Assessment for an Electricity Infrastructure Project. SIGn Jurnal Hukum, 6(2), 282-295. https://doi.org/10.37276/sjh.v6i2.389

Sumantri, M. F. A., Sami’an, S., & Hardjomuljadi, S. (2025). Concurrent Delay and Price Adjustment in Multi-Year Contracts: An Indonesian Construction Law Perspective. SIGn Jurnal Hukum, 6(2), 343-367. https://doi.org/10.37276/sjh.v6i2.399

Susanti, R., & Nurdiana, A. (2020). Cost Overrun in Construction Projects in Indonesia. In Proceedings of the Joint International Conference on Civil, Environmental, and Geo Engineering 2019 (Vol. 506, pp. 1-5). IOP Conference Series: Earth and Environmental Science. https://doi.org/10.1088/1755-1315/506/1/012039

Szarszoń, K. (2022). Legal Mechanisms for Adapting Contracts to Changing Economic Conditions in Professional Dealings. Wroclaw Review of Law, Administration & Economics, 11(2), 48-68. https://doi.org/10.2478/wrlae-2021-0017

Utama, N. A., & Sutrisno, B. (2023). Tanggung Jawab Pelaksana Konstruksi atas Keterlambatan Pembangunan karena Bencana Alam. Commerce Law, 3(1), 32-38. https://doi.org/10.29303/commercelaw.v3i1.2808

Wisatrioda, B., Sebastian, R. R., Sami’an, S., & Hardjomuljadi, S. (2025). Resolving Hydropower Plant Construction Disputes through a Standing Dispute Board: A Case Study of Asahan 3 HEPP. SIGn Jurnal Hukum, 6(2), 296-312. https://doi.org/10.37276/sjh.v6i2.392

Yanuar, R., Saputro, A., & Sami’an, S. (2025). Sustainability of Infrastructure Development in Indonesia: A Legal Analysis of Price Adjustments in Construction Contracts. SIGn Jurnal Hukum, 6(2), 247-262. https://doi.org/10.37276/sjh.v6i2.385

You, J., Chen, Y., Wang, W., & Shi, C. (2018). Uncertainty, Opportunistic Behavior, and Governance in Construction Projects: The Efficacy of Contracts. International Journal of Project Management, 36(5), 795-807. https://doi.org/10.1016/j.ijproman.2018.03.002

Published
2025-02-15
How to Cite
Wisnuaji, H., Sami’an, S., & Hardjomuljadi, S. (2025). Interpretation of Schedule When Changes in Conditions: A Case Study of Price Adjustment in the Lampung Extra High Voltage Overhead Line Construction Contract. SIGn Jurnal Hukum, 6(2), 368-385. https://doi.org/10.37276/sjh.v6i2.400

Most read articles by the same author(s)

<< < 1 2